High-rise residential emergency preparation and rescue measures

(a) General requirements
The emergency preparedness and rescue measures of the project should be aimed at potential occupational health and safety accidents or emergencies, and ensure that in the event of an accident or emergency, there are responding procedures to deal with it to reduce the impact of accidents or emergencies and reduce losses. The main emergency items for this project are: strong typhoons, fires, and personal injury (including poisoning).
In response to strong typhoon emergency matters, the technical department is responsible for the preparation of rainy season construction plans and measures. The materials department is responsible for purchasing rainproof, windproof, blackout-proof materials and emergency food reserves. The safety management department is responsible for the specific implementation, and organizes the anti-taiwan task force. The project's anti-typhoon emergency plan will be implemented after review and approval by the general contracting project manager organization.
For fire emergency matters, the technical department is responsible for the preparation of the project "Fire Protection Plan" and "Fire Prevention Plan" (also can be used as the chapter of the construction organization design) in conjunction with "Construction Organization Design". The Department of Materials is responsible for the purchase, equipment and acceptance of project fire fighting materials, and safety. The management department is responsible for the use and management of fire fighting materials and organizes the establishment of a project fire brigade. The fire protection plan and the fire protection plan shall focus on the preparation of emergency preparedness and response measures for fire protection work in flammable and explosive areas such as material storage and oil depots. The plan and plan shall be implemented by the general contracting project manager and the director of security inspection.
For accidents and incidents such as personal injury or poisoning, the Safety Management Department is responsible for preparing a contingency plan for personal injury accidents and establishing first-aid measures and management systems. The on-site clinic is to be set up. There must be obvious signs on the door, equipped with doctors and nurses, and first-aid kits and emergency stretchers in the clinic. After a safety incident occurred on the construction site, the injured person should be sent to the medical office immediately for treatment and if necessary, sent to the hospital for treatment. The first-aid box in the clinic must be kept by special personnel, and it must not be locked, and dressings and expired medicines that exceed the disinfection period should be replaced on a regular basis, and should be promptly replenished after each emergency. At the same time, the establishment of external emergency contact information and transportation security measures, etc., the safety management department is responsible for the supervision and management of the implementation of this work. The project personal injury casualty emergency plan shall be implemented by the general contracting project manager organization after examination and approval.
Commonly used items: stretchers, thermometers, sphygmomanometers, stethoscopes, oxygen bags, disposable syringes and infusion devices, and emergency lights and flashlights.
The Safety Management Department is responsible for organizing anti-Taiwan, fire drills, and on-the-spot first-aid rehearsals at appropriate times to verify the integrity of the corresponding personnel's skills, equipment and equipment, the effectiveness of emergency measures, and the smooth flow of communication channels. The contents of the on-site drill include: promptly notify the relevant units and personnel, rescue (fire fighting, first aid on the scene of the wounded), evacuation and evacuation, protection of important property, and closure of the site. The project safety and civilized construction management department completes and saves the records (including the live exercise photos).
(2) Emergency plan 1, emergency and emergency situations Prevent and control emergent emergencies such as natural disasters, diseases, major human-safety incidents, etc. to reduce their work on construction and operation, work and life of workers, and Impact on the public.
The on-site manager department has emergency response teams, and emergency response teams consist of general contracting project managers, project deputy managers, security inspection directors, department heads, professional technical leaders, and other related personnel. The general contracting project manager is the first person responsible for the emergency response team, and serves as the head of the emergency team. The project assistant manager, the security inspection director and the department head are the deputy heads of the emergency team.
As soon as an emergency event is confirmed, the emergency team starts immediately.
2. Emergency Procedures When an emergency occurs, informed persons and witnesses shall promptly report to the person in charge of the emergency team, and must immediately take emergency measures to deal with the situation. In accordance with the requirements of the emergency plan, the emergency situation and emergency Measures and current status are reported to the company headquarters emergency response team. When the situation is serious and it is difficult to handle it effectively, it should immediately contact the headquarters and the relevant social organizations for emergency relief.
When an emergency threatens personal safety, the person in charge of the unit must first ensure personal safety, organize personnel to rapidly escape dangerous areas or locations, and take emergency measures to minimize the impact on the environment and people.
The measures that can be taken in the event of an emergency include, but are not limited to, evacuation of people, emergency rescue, reporting to headquarters, and making a call to rescue.
In the emergency response handling process, relevant units and personnel shall pay attention to the collection and arrangement of emergency records related to emergencies, including but not limited to: information communication records, process control records, meeting minutes, documentation, photos, etc. .
3. Contingency handling of public health emergencies Public health emergencies refer to major epidemics, mass unexplained diseases, major food and occupational poisoning and other serious diseases that suddenly occur, cause or may cause serious public health damage. Events that affect public health.
All subcontracted units and individuals shall report the situation to the daily management department of the emergency department of the emergency management department, ie the safety management department, as soon as possible after discovering or understanding infectious diseases. The contracting project manager is responsible for reporting to nearby health care institutions or health and anti-epidemic agencies in accordance with laws and regulations within the shortest possible time.
Members of the general contracting project manager, members of the subcontractors, workers or their families or persons with whom they have close contact have or are suspected of having an infectious disease. The employee should immediately report the situation to the Department of Safe and Civilized Construction Management and take immediate isolation measures to proceed. Infectious disease hospital. According to the "Infectious Diseases Prevention and Control Law", the environment to be contacted is sterilized, and the individuals who are in contact with it are observed, isolated, and treated for medical treatment.
No unit or individual may conceal, misrepresent or inspire others to conceal or falsely report the epidemic situation.
The general contracting project manager, all subcontracted units and employees must receive inquiry, inspection, investigation and evidence collection, and prevention and control measures for infectious diseases from health care institutions, health and anti-epidemic agencies, and have the right to report and confess violations of the "Infectious Diseases Prevention and Control Act." behavior.
The unit emergency response team shall report the outbreak to the relevant unit in accordance with the provisions of national laws and regulations.
4. Emergency treatment of natural disasters Natural disasters include earthquakes, floods, heavy rain, and high winds.
After a natural disaster occurs, the general contracting project manager and the company shall organize various forces, rescue personnel, organize and carry out self-rescue and mutual rescue, and follow the arrangement of emergency response teams.
After a natural disaster occurs, the general contracting project manager and the headquarters shall promptly establish communication links with relevant units to report the disaster and formulate a rescue plan.
After a natural disaster occurs, the affected units should first check the casualties and give priority to rescue personnel.
After the natural disaster occurs, the general contracting project manager and the headquarters of the Bureau shall actively arrange the disaster victims to properly arrange their accommodation and other basic living conditions so as to ensure that they are no longer affected by natural disasters.
After a natural disaster occurs, the headquarters and affected units of the unit shall notify the relatives of the victims, the relevant government departments, industry associations, and the community about the disaster through any effective means.
After a natural disaster occurs, the unit headquarters and affected units should actively organize disaster reconstruction and formulate reconstruction plans.
5. Emergency handling of other emergencies (1) Fire treatment Fire control equipment should be provided in accordance with relevant regulations to train the use of equipment.
In the event of a fire, the unit where the fire is located should organize the rescue as soon as possible and call the rescue telephone 119 to report the public security fire department.
While organizing fire extinguishing, flammable and explosive materials should be isolated as far as possible to avoid explosion.
After a fire accident occurs, the unit where the fire is located should do a good job of on-site protection and conduct on-site survey work with the fire department.
2. The chemical leakage treatment shall immediately report the incident to the relevant department for professional rescue.
If the leaked chemical is highly toxic or highly volatile, emergency evacuation and rescue should be arranged immediately.
Only persons who have taken appropriate personal protection and have received necessary training can clean up the site of chemical dangerous goods leaked, and other personnel should maintain a certain safety distance from the leakage site.
Places that are contaminated with chemical substances should be promptly cleaned up. All pollutants generated during the clean-up process should be disposed of as chemical waste.

Copyright statement: The information section and comments as well as the contents of the text, except for the original articles of China Labor Insurance Net, are all reproduced by publishers or other online media. They only represent the views of the authors and have nothing to do with the China Labor Insurance Network. If news articles and comments infringe your legal rights, please call us and we will handle it in a timely manner.

Shaker screen:When it comes to a solid control system on any type of drilling equipment, the shale shaker is arguably the most important pieces of equipment. With drilling fluid being so important to maintaining drill performance, being able to utilize fluid efficiently is crucial. A shale shaker is what separates any drilling liquid, commonly referred to as mud, from solids, also known as cuttings. On a shale shaker, one of the most important components is the Shale Shaker Screen. The shale shaker screen is actually what separates liquids from solids so having the correct screen can determine how effective drilling equipment operates.The shale shaker screen is a mesh screen that is created out of woven metal that goes inside the shale shaker. Whenever solids or cuttings are produced from drilling equipment, they are coated in drilling liquid. When those cuttings are shaken over shale shaker screens, the screen is able to capture all of the solid particles and allow any excess mud to drip through the screen where it can then be deposited back into the tank.

Oil Shale Shaker Screen Series

Oil Shale Shaker Screen Series, Composite Frame Shaker Screen, Composite Soft Screen, Hook Strip Flat Screen

Anping Shengjia Hardware Mesh Co.,LTD , https://www.oilshaleshakerscreen.com